top of page
ASHDOD MATASH

ASHDOD, ISRAEL

Shtang is upgrading the Ashdod WwTP to a tertiary treatment level and enlarging its capacity. This is done by constructing a gravitational sand filtering system, improving the bioreactors, reconstructing the primary scrapers, erecting new secondary clarifiers and tanks, and more.

 

The works included, inter alia, civil works and sealing, construction and refurbishment buildings, supply and installation of electromechanical equipment, supply and installation of instrumentation and a command & control system, as well as startup and commissioning of the upgraded and enlarged  facility.

ISRAEL.png

CAPACITY

STATUS

Raw Material

Annual quantity

55,000 m3/d

Grid connection approval, ready to start construction

Water&
Waste water

55,000 m3/d

bottom of page