Slutsk WWTP (Belarus)

Design and full reconstruction of municipal waste water facility with the capacity of 30,000 m3/day. The scope includes: process and detailed design, construction of the new collector, construction/reconstruction of mechanical treatment, primary sedimentation, biological treatment and blowers replacement, piping, sludge sickening, electrical and automation works. The project is financed by World Bank.

CAPACITY

30,000 m3/day

STATUS

Design