Grodno WWTP (Belarus)
Reconstruction and upgrade of municipal waste water facility to include nitrogen and phosphorus removal with the capacity of 115,000 m3/day (~400,000 P.E.). The scope includes: design of additional works and buildings, construction/reconstruction of mechanical treatment, primary sedimentation, biological treatment and blowers replacement, secondary sedimentation, piping, sludge sickening, electrical and automation works as well as addition of 3 new pumping stations. The project is financed by Nordic Investment Bank loans, SIDA and NDEP grants and is aimed to reduce the pollution of the Baltic sea.

CAPACITY
110,000 m3/day
STATUS
Construction
Raw Material
Waste water