ASHDOD

3,000 m3/d

The goal of the project was to transfer three 2.5-meter pipes. Each channel is 50 meters long. The purpose of two of the three pipes is to bring water from the sea to the desalination plant. And the third pipe returns the salt from the desalination plant to the sea/ The duration of the project is 3 months. The work was pressured by a 1-team atmosphere that Stang.
 

worked inside the shaft at a depth of 12.5 meters below sea level And we used divers to see that everything was in place and there were no stones stuck on the way The removal was done carefully not to damage two gas pipes on our way and to make sure that the sand did not move and cause the gas to move. To this day the facility works without a hitch
 