Construction, commissioning and O&M for a five year period, for the Holit WWTP, including upgrading of the old treatment pools and effluent reservoir of the old plant.
The facility was built using the Sequenced Batch Reactor (SBR) technology and treats wastewater to a tertiary level, by pressure sand filtration. Works included earthworks, civil works, sealing, pipe laying, valves, gates, etc., sanitary installation works; supply and installation, start-up and commissioning of equipment, instrumentation, electrical and control systems; site development and landscape, etc.

CAPACITY
3,000 M3/d
STATUS
O&M period
Raw Material
Waste water