top of page

KIRIAT GAT, ISRAEL
Shtang supplied and installed equipment, completed civil works, electrical and control systems, piping, etc. in the WWTP to upgrade it to tertiary level. In addition, the treatment process was modified.
The works included, inter alia, effluent pipe laying, supply of equipment, construction and commissioning of a chlorination system, supply of equipment and erection of a tertiary treatment facility (including the construction of a contact tank, piping, and holding tank), conversion of three reactors to tertiary treatment, including refurbishment, the construction of odor control systems and a command and control system for the entire wastewater treatment facility.

CAPACITY
24,000 m3/d
STATUS
Operating
Raw Material
Waste water